Document
Number |
Title |
Date
Published |
Author |
Author
Affiliation |
|
01634 |
REVISED FINAL
PROJECT PLANS FOR THE X-RAY FLUORESCENCE PILOT STUDY AT SITE 4B ALLEGANY
BALLISTICS LABORATORY WEST VIRGINIA |
10/1/2003 |
|
CH2M HILL |
|
01656 |
LETTER
NOTIFYING THE U S NAVY THAT WVADEP HAS NO ADDITIONAL COMMENTS ON THE
FINAL WORK PLAN ADDENDUM FOR PHASE IV INVESTIGATIONS AT SWMU 2 AND SWMU
27A AND REMOVAL ACTIVITIES AT SWMU 37II ALLEGANY BALLISTICS LABORATORY
WEST VIRGINIA |
2/19/2004 |
T BASS |
WVADEP |
|
01665 |
FINAL 2004
SITE MANAGEMENT PLAN ALLEGANY BALLISTICS LABORATORY WEST VIRGINIA |
4/1/2004 |
|
CH2M HILL |
|
01666 |
TRANSMITTAL
LETTER FOR THE FINAL PROPOSED REMEDIAL ACTION PLAN SITE 7 THE FORMER
BERYLLIUM LANDFILL ALLEGANY BALLISTICS LABORATORY WEST VIRGINIA |
5/17/2001 |
B DOERR |
CH2M HILL |
|
01669 |
FINAL WORK
PLAN FOR SITE 1 SOILS BASELINE ECOLOGICAL RISK ASSESSMENT STEP 4
ALLEGANY BALLISTICS LABORATORY WEST VIRGINIA |
3/1/2004 |
|
CH2M HILL |
|
01671 |
FINAL
TECHNICAL MEMORANDUM BACKGROUND SOIL INVESTIGATION ALLEGANY BALLISTICS
LABORATORY WEST VIRGINIA |
3/29/2004 |
S GLENNIE |
CH2M HILL |
|
01672 |
TRANSMITTAL
LETTER FOR THE FINAL WORK PLAN FOR SITE 1 SOILS BASELINE ECOLOGICAL RISK
ASSESSMENT STEP 4 ALLEGANY BALLISTICS LABORATORY WEST VIRGINIA |
3/30/2004 |
S GLENNIE |
CH2M HILL |
|
01678 |
LETTER AND
COMMENTS ON THE FINAL BACKGROUND SOIL INVESTIGATION TECHNICAL MEMORANDUM
ALLEGANY BALLISTICS LABORATORY WEST VIRGINIA |
6/21/2004 |
T BASS |
WVADEB |
|
01679 |
LETTER NOTING
THAT WVADEP HAS NO ADDITIONAL COMMENTS ON THE FNAL WORK PLAN FOR SITE 1
SOILS BASELINE ECOLOGICAL RISK ASSESSMENT STEP 4 ALLEGANY BALLISTICS
LABORATORY WEST VIRGINIA |
6/21/2004 |
T BASS |
WVADEP |
|
01680 |
LETTER NOTING
THAT WVADEP HAS NO ADDITIONAL COMMENTS ON THE FINAL WORK PLAN ADDENDUM
SITE 12 BEDROCK DYE TRACING AND YIELD TESTING ALLEGANY BALLISTICS
LABORATORY WEST VIRGINIA |
6/21/2004 |
T BASS |
WVADEP |
|
01681 |
LETTER NOTING
THAT WVADEP HAS NO ADDITIONAL COMMENTS ON THE FINAL 2004 SITE MANAGEMENT
PLAN FOR ALLEGANY BALLISTICS LABORATORY WEST VIRGINIA |
6/23/2004 |
T BASS |
WVADEP |
|
01683 |
LETTER
CONCURRING WITH THE REMOVAL ACTION FOR THE REVISED DRAFT SITE 12 SOIL
ENGINEERING EVALUATION AND COST ANALYSIS FOR ALLEGANY BALLISTICS
LABORATORY WEST VIRGINIA |
6/29/2004 |
T BASS |
WVADEP |
|
01684 |
RECORD OF
DECISION SITE 10 FORMER TCE STILL AND PLANT PRODUCTION WELLS "A" AND "C"
GROUNDWATER OPERABLE UNIT 5 (OU 5) ALLEGANY BALLISTICS LABORATORY WEST
VIRGINIA |
9/1/2004 |
|
NAVFAC
ATLANTIC |
|
01690 |
LETTER NOTING
WVADEP HAS COMPLETED ITS REVIEW AND HAS NO ADDITIONAL COMMENTS ON THE
SITE 12 DYE TRACING AND YEILD TESTING RESULTS ALLEGANY BALLISTICS
LABORATORY WEST VIRGINIA |
3/17/2005 |
T BASS |
WVADEP |
|
01691 |
LETTER
INDICATING WVADEP HAS COMPLETED ITS REVIEW AND PROVIDES CONDITIONAL
CONCURRENCE FOR THE FINAL WORK PLAN FOR IN SITU CHEMICAL OXIDATION PILOT
STUDY AT THE SOLVENT DISPOSAL PIT AREA OF SITE 1 ALLEGANY BALLISTICS
LABORATORY WEST VIRGINIA |
5/2/2005 |
T BASS |
WVADEP |
|
01693 |
TRANSMITTAL
LETTER FOR THE FINAL RISK ASSESSMENT FOR SITE 10 SOIL AND SITES 2 AND 3
ALLEGANY BALLISTICS LABORATORY WEST VIRGINIA |
7/25/2005 |
S GLENNIE |
CH2M HILL |
|
01694 |
FINAL RISK
ASSESSMENT REPORT FOR SITE 10 SOIL AND SITES 2 AND 3 ALLEGANY BALLISTICS
LABORATORY WEST VIRGINIA |
7/1/2005 |
|
CH2M HILL |
|
01695 |
TRANSMITTAL
LETTER FOR FINAL 2005 SITE MANAGEMENT PLAN ALLEGANY BALLISTIC LABORATORY
ROCKET CENTER WEST VIRGINIA |
9/2/2005 |
S GLENNIE |
CH2M HILL |
|
01697 |
FINAL 2005
SITE MANAGEMENT PLAN ALLEGANY BALLISTICS LABORATORY WEST VIRGINIA |
8/1/2005 |
|
CH2M HILL |
|
01701 |
FINAL SOLID
WASTE MANAGEMENT UNITS REMOVAL ACTION REPORT ALLEGANY BALLISTICS
LABORATORY WEST VIRGINIA |
5/1/2005 |
|
CH2M HILL |
|
01702 |
FINAL WORK
PLAN FOR THE CHARACTERIZATION PHASE OF PILOT STUDIES AT THE SOLVENT
DISPOSAL PIT AREA OF SITE 1 ALLEGANY BALLISTICS LABORATORY WEST VIRGINIA |
11/1/2004 |
|
CH2M HILL |
|
01704 |
MASTER HEALTH
AND SAFETY PLAN FOR THE ALLEGANY BALLISTICS LABORATORY INSTALLATION
RESTORATION PROGRAM ALLEGANY BALLISTICS LABORATORY WEST VIRGINIA |
10/1/2006 |
|
CH2M HILL |
|
01712 |
FINAL WORK
PLAN FOR A PILOT STUDY AT THE RANGE ROAD AREA OF SWMU 27A ALLEGANY
BALLISTICS LABORATORY WEST VIRGINIA |
9/1/2004 |
|
CH2M HILL |
|
01713 |
FINAL WORK
PLAN FOR IN SITU CHEMICAL OXIDATION PILOT STUDY AT THE SOLVENT DISPOSAL
PIT AREA OF SITE 1 ALLEGANY BALLISTICS LABORATORY WEST VIRGINIA |
4/1/2005 |
|
CH2M HILL |
|
01715 |
U S NAVY
RESPONSE TO U S EPA REGION III COMMENTS ON THE DRAFT RISK ASSESSMENT
REPORT FOR SITE 10 SOIL AND SITES 2 AND 3 ALLEGANY BALLISTICS LABORATORY
WEST VIRGINIA |
6/28/2005 |
|
NAVFAC MID
ATLANTIC |
|
01718 |
LETTER NOTING
THAT WVADEP HAS NO COMMENTS ON THE DRAFT PRELIMNARY REMEDIATION GOALS
FOR SITE 4B SOILS TECHNICAL MEMORANDUM ALLEGANY BALLISTICS LABORATORY
WEST VIRGINIA |
8/28/2002 |
T BASS |
WVADEP |
|
01719 |
LETTER NOTING
THAT WVADEP HAS NO COMMENTS ON THE DRAFT FINAL PROJECT PLANS FOR THE
X-RAY FLOURESENCE PILOT STUDY AT SITES 4B AND 10 ALLEGANY BALLISTICS
LABORATORY WEST VIRGINIA |
8/26/2002 |
T BASS |
WVADEP |
|
01720 |
FINAL SITE 12
SOIL REMOVAL ACTION REPORT ALLEGANY BALLISTICS LABORATORY WEST VIRGINIA |
11/1/2005 |
|
CH2M HILL |
|
01721 |
SWMU CLOSEOUT
PACKAGE FOR AOC H CENTRIFUGE ALLEGANY BALLISTICS LABORATORY WEST
VIRGINIA |
2/13/2002 |
|
CH2M HILL |
|
01722 |
SWMU CLOSEOUT
PACKAGE FOR ALLEGANY BALLISTICS LABORATORY WEST VIRGINIA |
2/14/2002 |
|
LANTDIV |
|
01723 |
LETTER AND
COMMENTS ON THE DRAFT PROPOSED METHODS FOR PREPARING THE HUMAN HEALTH
RISK ASSESSMENT SITE 1 ALLEGANY BALLISTICS LABORATORY WEST VIRGINIA |
7/3/2002 |
B BEACH |
U S EPA REGION
III |
|
01724 |
LETTER
CONCURRING WITH EVALUTION PRESENTED IN THE DRAFT PHASE III AQUIFER
TESTING AT SITE 1 AND SITE 10 WITH ADDITIONAL COMMENTS ON THE REPORT
ALLEGANY BALLISTICS LABORATORY WEST VIRGINIA |
1/4/2002 |
B BEACH |
U S EPA REGION
III |
|
01725 |
SWMU CLOSEOUT
PACKAGE AOC P FORMER GROUND SCAR AREA ALLEGANY BALLISTICS LABORATORY
WEST VIRGINIA |
9/28/2005 |
|
|
|
01726 |
RECORD OF
DECISION SITE 10 FORMER TCE STILL AND PLANT PRODUCTION WELLS "A" AND "C"
GROUNDWATER OPERABLE UNIT 5 (OU 5) ALLEGANY BALLISTICS LABORATORY WEST
VIRGINIA |
8/1/2005 |
|
CH2M HILL |
|
01733 |
TRANSMITTAL
LETTER FOR THE FINAL AOC P CLOSEOUT DOCUMENT ALLEGANY BALLISTICS
LABORATORY WEST VIRGINIA |
10/5/2005 |
S GLENNIE |
CH2M HILL |
|
01737 |
LETTER
CONCURRING WITH THE SITE 5 DRAFT RECORD OF DECISION FOR GROUNDWATER
SURFACE WATER AND SEDIMENT ALLEGANY BALLISTICS LABORATORY WEST VIRGINIA |
7/7/2005 |
T BASS |
WVADEP |
|
01738 |
LETTER NOTING
THAT WVADEP HAS COMPLETED ITS REVIEW AND HAS NO COMMENTS ON THE DRAFT
RISK ASSESSMENT REPORT FOR SITE 10 SOIL AND SITE 2 AND 31 ALLEGANY
BALLISTICS LABORATORY WEST VIRGINIA |
5/31/2005 |
T BASS |
WVADEP |
|
01739 |
SWMU CLOSEOUT
PACKAGE SWMU 37II BUILDING 49 WASTEWATER SUMP ALLEGANY BALLISTICS
LABORATORY WEST VIRGINIA |
1/20/2005 |
|
CH2M HILL |
|
01741 |
FINAL WORK
PLAN ADDENDUM FOR PHASE IV INVESTIGATIONS AT SWMUS 2 AND 27A AND REMOVAL
ACTIVITES AT SWMU 37II ALLEGANY BALLISTICS LABORATORY WEST VIRGINIA |
1/1/2004 |
|
CH2M HILL |
|
01742 |
TRANSMITTAL
LETTER FOR THE FINAL WORK PLAN ADDENDUM FOR PHASE V INVESTIGATION OF
SWMU 27A ALLEGANY BALLISTICS LABORATORY WEST VIRGINIA |
11/16/2005 |
S GLENNIE |
CH2M HILL |
|
01743 |
FINAL WORK
PLAN ADDENDUM FOR ADDITIONAL SOIL SAMPLING ACTIVITIES AT AOC R ALLEGANY
BALLISTICS LABORATORY WEST VIRGINIA |
12/1/2005 |
|
CH2M HILL |
|
01744 |
FINAL WORK
PLAN ADDENDUM FOR PHASE V INVESTIGATION AT SWMU 27A ALLEGANY BALLISTICS
LABORATORY WEST VIRGINIA |
11/1/2005 |
CH2M HILL |
|
|
01745 |
ACTION
MEMORANDUM DESCRIBING THE NON-TIME CRITICAL REMOVAL ACTION TO BE
CONDUCTED UNDER CERCLA FOR SOIL AT SITE 12 BUILDING 167 AND SURROUNDINGS
ALLEGANY BALLISTICS LABORATORY WEST VIRGINIA |
8/2/2004 |
S MARTIN |
LANTDIV |
|
01746 |
TRANSMITTAL
LETTER FOR THE FINAL SITE 12 SOIL ENGINEERING EVALUATION AND COST
ANALYSIS WORK PLAN ADDENDUM ALLEGANY BALLISTICS LABORATORY WEST VIRGINIA |
8/23/2004 |
S GLENNIE |
CH2M HILL |
|
01747 |
FINAL SITE 12
SOIL ENGINEERING EVALUATION AND COST ANALYSIS ALLEGANY BALLISTICS
LABORATORY WEST VIRGINIA |
8/1/2004 |
|
CH2M HILL |
|
01748 |
FINAL REMEDIAL
INVESTIGATION REPORT FOR SITE 11 PRODUCTION WELL "F" ALLEGANY BALLISTICS
LABORATORY WEST VIRGINIA |
1/1/2005 |
|
CH2M HILL |
|
01749 |
LETTER
INDICATING THAT THE U S EPA REGION III HAS NO FURTHER COMMENT ON THE
FINAL WORK PLAN PILOT STUDY RANGE ROAD AREA OF SWMU 27A ALLEGANY
BALLISTICS LABORATORY ROCKET CENTER WEST VIRGINIA |
1/6/2006 |
M STEPHENS |
U S EPA REGION
III |
|
01750 |
LETTER
INDICATING THAT THE U S EPA REGION III HAS NO FURTHER COMMENT ON THE
FINAL WORK PLAN ISCO PILOT STUDY SITE 1 ALLEGANY BALLISTICS LABORATORY
ROCKET CENTER WEST VIRGINIA |
1/6/2006 |
M STEPHENS |
U S EPA REGION
III |
|
01751 |
LETTER
INDICATING THAT THE U S EPA REGION III HAS NO FURTHER COMMENT ON THE
FINAL RISK ASSESSMENT REPORT SITE 10 SOIL AND SITES 2 AND 3 ALLEGANY
BALLISTICS LABORATORY ROCK CENTER WEST VIRGINIA |
1/6/2006 |
M STEPHENS |
U S EPA REGION
III |
|
01752 |
LETTER
INDICATING THAT THE U S EPA REGION III HAS NO FURTHER COMMENT ON THE
FINAL FOCUSED REMEDIAL INVESTIGATION FEASIBILITY STUDY FOR SITE 5
GROUNDWATER SURFACE WATER AND SEDIMENT ALLEGANY BALLISTICS LABORATORY
ROCKET CENTER WEST VIRGINIA |
1/6/2006 |
M STEPHENS |
U S EPA REGION
III |
|
01753 |
LETTER
INDICATING THAT THE U S EPA REGION III HAS NO FURTHER COMMENT ON THE
FINAL SITE 12 SOIL REMOVAL ACTION REPORT ALLEGANY BALLISTICS LABORATORY
ROCKET CENTER WEST VIRGINIA |
1/6/2006 |
M STEPHENS |
U S EPA REGION
III |
|
01754 |
LETTER
INDICATING THAT THE U S EPA REGION III HAS NO FURTHER COMMENT ON THE
FINAL SOLID WASTE MANAGEMENT UNITS REMOVAL ACTION REPORT ALLEGANY
BALLISTICS LABORATORY ROCKET CENTER WEST VIRGINIA |
1/6/2006 |
M STEPHENS |
U S EPA REGION
III |
|
01755 |
LETTER
INDICATING THAT THE U S EPA REGION III HAS NO FURTHER COMMENT ON THE
FINAL 2005 SITE MANAGEMENT PLAN ALLEGANY BALLISTICS LABORATORY ROCKET
CENTER WEST VIRGINIA |
1/6/2006 |
M STEPHENS |
U S EPA REGION
III |
|
01756 |
LETTER
INDICATING THAT THE U S EPA REGION III HAS NO FURTHER COMMENT ON THE
FINAL PHASE II SWMU INVESTIGATION REPORT ALLEGANY BALLISTICS LABORATORY
ROCKET CENTER WEST VIRGINIA |
1/6/2006 |
M STEPHENS |
U S EPA REGION
III |
|
01757 |
LETTER
INDICATING THAT THE U S EPA REGION III HAS NO FURTHER COMMENT ON THE
FINAL PHASE III/IV SOLID WASTE MANAGEMENT UNIT INVESTIGATION REPORT
ALLEGANY BALLISTICS LABORATOY ROCKET CENTER WEST VIRGINIA |
1/6/2006 |
M STEPHENS |
U S EPA REGION
III |
|
01759 |
FINAL SITE 4B
PILOT STUDY REPORT ALLEGANY BALLISTICS LABORATORY ROCKET CENTER WEST
VIRGINIA |
3/1/2006 |
|
CH2M HILL |
|
01764 |
TRANSMITTAL
LETTER FOR FINAL 2006 SITE MANAGEMENT PLAN ALLEGANY BALLISTICS
LABORATORY ROCKET CENTER WEST VIRGINIA |
7/13/2006 |
S GLENNIE |
CH2M HILL |
|
01765 |
FINAL 2006
SITE MANAGEMENT PLAN ALLEGANY BALLISTICS LABORATORY ROCKET CENTER WEST
VIRGINIA |
7/1/2006 |
|
CH2M HILL |
|
01766 |
PROPOSED
REMEDIAL ACTION PLAN FOR SITE 2 ALLEGANY BALLISTICS LABORATORY WEST
VIRGINIA |
7/18/2006 |
|
CH2M HILL |
|
01767 |
PROPOSED
REMEDIAL ACTION PLAN FOR SITE 10 ALLEGANY BALLISTICS LABORATORY WEST
VIRGINIA |
7/18/2006 |
|
CH2M HILL |
|
01768 |
PROPOSED
REMEDIAL ACTION PLAN FOR SITE 3 ALLEGANY BALLISTICS LABORATORY WEST
VIRGINIA |
7/18/2006 |
|
CH2M HILL |
|
01769 |
FINAL WORK
PLAN FOR ECOLOGICAL INVESTIGATIONS IN THE NORTH POTOMAC RIVER SITE 1
BASELINE ECOLOGICAL RISK ASSESSMENT STEP 4 ALLEGANY BALLISTICS
LABORATORY WEST VIRGINIA |
8/1/2006 |
|
CH2M HILL |
|
01770 |
TRANSMITTAL
LETTER FOR THE DRAFT SITE 12 ENGINEERING ESTIMATE AND COST ANALYSIS AT
ALLEGAY BALLISTICS LABORATORY WEST VIRGINIA |
5/19/2004 |
S GLENNIE |
CH2M HILL |
|
01771 |
PUBLIC NOTICE
OF THE NAVY'S INVITATION FOR PUBLIC COMMENTS ON THE ENGINEERING
EVALUATION/COST ANALYSIS FOR SITE 12 SOIL ALLEGANY BALLISTICS LABORATORY
WEST VIRGINIA |
6/6/2004 |
|
NAVFAC MID
ATLANTIC |
|
01780 |
RESTORATION
ADVISORY BOARD MEETING MINUTES FOR 8 AUGUST 2006 ALLEGANY BALLISTICS
LABORATORY WEST VIRGINIA |
8/8/2006 |
|
CH2M HILL |
|
01781 |
TRANSCRIPT OF
PROCEEDINGS FOR THE PUBLIC MEETING HELD 8 AUGUST 2006 DISCUSSING THE
PROPOSED REMEDIAL ACTION PLAN FOR SITE 2, SITE 3 AND SITE 10 ALLEGANY
BALLISTICS LABORATORY WEST VIRGINIA |
8/8/2006 |
|
|
|
01784 |
EMAIL
INDICATING U S EPA HAS COMPLETED REVIEW OF THE DRAFT SITE 5 PERMEABLE
REACTIVE BARRIER WORK PLAN AND THE DOCUMENT ADEQUATELY SPECIFIES WORK TO
COMPLETE INSTALLATION ALLEGANY BALLISTICS LABORATORY WEST VIRGINIA |
5/31/2006 |
T RICHARDSON |
U S EPA REGION
III |
|
01785 |
EMAIL
INDICATING U S EPA HAS NO FURTHER COMMENTS ON DRAFT 2006 SITE MANAGEMENT
PLAN ALLEGANY BALLISTICS LABORATORY WEST VIRGINIA |
5/31/2006 |
T RICHARDSON |
U S EPA REGION
III |
|
01787 |
EMAIL
INDICATING U S EPA HAS NO ADDITIONAL COMMENTS ON THE SITE 5 WORK PLAN
ALLEGANY BALLISTICS LABORATORY WEST VIRGINIA |
3/22/2006 |
T RICHARDSON |
U S EPA REGION
III |
|
01793 |
FEDERAL
REGISTER NOTICE OF THE NATIONAL PRIORITIES LIST FOR UNCONTROLLED
HAZARDOUS WASTE SITES LISTING ALLEGANY BALLISTICS LABORATORY WEST
VIRGINIA |
4/1/1997 |
|
FEDERAL
REGISTER |
|
01794 |
LETTER IN
RESPONSE TO THE U S NAVY LETTER REGARDING THE DISCHARGE OF AMMONIUM
PERCHLORATE FROM THE SITE 1 GROUNDWATER TREATMENT PLANT ALLEGANY
BALLISTICS LABORATORY WEST VIRGINIA |
2/20/2000 |
K ELLISON |
WVADEP |
|
01795 |
LETTER
REQUESTING THAT SWMU 37C, SWMU 37BB, SWMU 40, AOC M AND AOC O BE
INCORPORATED OR TRANSFERRED FROM APPENDIX A TO APPENDIX B FOR THE
FEDERAL FACILITY AGREEMENT ALLEGANY BALLISTICS LABORATORY WEST VIRGINIA |
2/21/2001 |
D OCONNOR |
LANTDIV |
|
01796 |
TECHNICAL
MEMORANDUM DATA EVALUATION OF CONTAINER STORAGE AREAS FINAL WASTE
CHARACTERIZATION ALLEGANY BALLISTICS LABORATORY WEST VIRIGNIA |
5/15/2001 |
E PITERA |
CH2M HILL |
|
01797 |
TECHNICAL
MEMORANDUM DATA EVALUATION OF BURNING GROUNDS FINAL WASTE
CHARACTERIZATION ALLEGANY BALLISTICS LABORATORY WEST VIRGINIA |
5/17/2001 |
E PITERA |
CH2M HILL |
|
01798 |
TECHNICAL
MEMORANDUM HUMAN HEALTH RISK ASSESSMENT OF CURRENT CONDITIONS BURNING
GROUNDS ALLEGANY BALLISTICS LABORATORY WEST VIRGINIA |
10/1/2001 |
|
CH2M HILL |
|
01799 |
TRANSMITTAL
LETTER FOR THE TECHNICAL MEMORANDUM HUMAN HEALTH RISK ASSESSMENT OF
CURRENT CONDITIONS BURNING GROUNDS ALLEGANY BALLISTICS LABORATORY WEST
VIRIGNIA |
10/8/2001 |
J WAUGAMAN |
ALLIANT TECH
SYSTEMS |
|
01800 |
TRANSMITTAL
LETTER FOR THE DRAFT TECHNICAL MEMORANDUM ECOLOGICAL RISK ASSESSMENT
METHODOLOGY AND CURRENT CONDITIONS BURNING GROUNDS ALLEGANY BALLISTICS
LABORATORY WEST VIRGINIA |
10/9/2001 |
J WAUGAMAN |
|
|
01801 |
TRANSMITTAL
LETTER FOR THE TECHNICAL MEMORANDUM HUMAN HEALTH RISK ASSESSMENT OF
FACILITY OPERATIONS BURNING GROUNDS ALLEGANY BALLISTICS LABORATORY WEST
VIRGINIA |
10/23/2001 |
J WAUGAMAN |
|
|
01803 |
TRANSMITTAL
LETTER FOR THE FINAL WORK PLAN ADDENDUM FOR PHASE III INVESTIGATIONS AT
SWMU 27A AND SWMU 37V AND FOR REMEDIAL INVESTIGATION OF SITE 12 ALLEGANY
BALLISTICS LABORATORY WEST VIRGINIA |
1/17/2003 |
S GLENNIE |
CH2M HILL |
|
01804 |
FINAL HUMAN
HEALTH RISK ASSESSMENT PROTOCOL FOR THE BURNING GROUNDS ALLEGANY
BALLISTICS LABORATORY WEST VIRGINIA |
7/1/2003 |
|
CH2M HILL |
|
01805 |
FINAL
ECOLOGICAL RISK ASSESSMENT PROTOCOL FOR THE BURNING GROUNDS ALLEGANY
BALLISTICS LABORATORY WEST VIRGINIA |
7/1/2003 |
|
CH2M HILL |
|
01809 |
REVISED
ADDENDUM TO THE FINAL TECHNICAL MEMORANDUM PRELIMINARY REMEDIATION GOALS
FOR SITE 4B SOIL ALLEGANY BALLISTICS LABORATORY WEST VIRGINIA |
11/5/2003 |
D CONNNOR |
LANTDIV |
|
01810 |
TRANSMITTAL
LETTER FOR THE FINAL HYDROLOGIC INVESTIGATION REPORT FOR THE SANITARY
AND TORM SEWER LINE IN THE VICINITY OF SITE 10 ALLEGANY BALLISTICS
LABORATORY |
1/28/2004 |
S GLENNIE |
CH2M HILL |
|
01811 |
TRANSMITTAL
LETTER FOR THE FINAL WORK PLAN ADDENDUM FOR PHASE IV INVESTIGATIONS AT
SWMU 2 AND SWMU 27A AND REMOVAL ACTIVITIES AT SWMU 37II ALLEGANY
BALLISTICS LABORATORY WEST VIRGINIA |
2/2/2004 |
S GLENNIE |
CH2M HILL |
|
01813 |
TECHNICAL
MEMORANDUM APPROACH FOR REVISED HUMAN HEALTH AND ECOLOGICAL RISK
ASSESSMENTS FOR SITE 1 SOIL AT ALLEGANY BALLISTICS LABORATORY WEST
VIRGINIA |
3/30/2004 |
|
CH2M HILL |
|
01814 |
TRANSMITTAL
LETTER FOR THE FINAL BACKGROUND SOIL INVESTIGATION TECHNICAL MEMORANDUM
ALLEGANY BALLISTICS LABORATORY WEST VIRGINIA |
3/30/2004 |
S GLENNIE |
CH2M HILL |
|
01815 |
TECHNICAL
MEMORANDUM FINAL WORK PLAN ADDENDUM SITE 12 BEDROCK DYE TRACING AND YELD
TESTING ALLEGANY BALLISTICS LABORATORY WEST VIRGINIA |
5/13/2004 |
|
CH2M HILL |
|
01817 |
LETTER OF
NOTIFICATION THAT THE U S NAVY MUST IMPLEMENT A METHODOLGY TO REDUCE OR
ELIMINATE THE AMMONIUM PERCHLORATE FROM THE EFFLUENT DISCHARGE FROM THE
SITE 1 GROUNDWATER TREATMENT PLANT ALLEGANY BALLISTICS LABORATORY WEST
VIRGINIA |
11/17/1999 |
T BASS |
WVADEP |
|
01818 |
DRAFT (FINAL
VERSION) SITE 1 FOCUSED FEASIBILITY STUDY ALLEGANY BALLISTICS LABORATORY
WEST VIRGINIA |
10/1/1995 |
|
CH2M HILL |
|
01820 |
TRANSMITTAL
LETTER FOR THE FINAL WORK PLAN FOR ECOLOGICAL INVESTIGATIONS IN THE
NORTH BRANCH POTOMAC RIVER SITE 1 ALLEGANY BALLISTICS LABORATORY WEST
VIRGINIA |
8/7/2006 |
S GLENNIE |
CH2M HILL |
|
01822 |
FINAL FOCUSED
REMEDIAL INVESTIGATION FOR SITE 1 SOIL AND OPERABLE UNIT 4 (OU 4)
ALLEGANY BALLISTICS LABORATORY WEST VIRGINIA |
7/1/2006 |
|
CH2M HILL |
|
01825 |
RECORD OF
DECISION FOR SITE 5 GROUNDWATER SURFACE WATER AND SEDIMENT OPERABLE UNIT
2 (OU 2) ALLEGANY BALLISTICS LABORATORY WEST VIRGINIA |
10/1/2005 |
|
CH2M HILL |
|
01828 |
FINAL WORK
PLAN ADDENDUM FOR ADDITIONAL CHARACTERIZATION ACTIVITIES FOR SITE 11,
SITE 12 AND RANGE ROAD AREA ALLEGANY BALLISTICS LABORATORY WEST VIRGINIA |
10/1/2006 |
|
CH2M HILL |
|
01842 |
PROPOSED
REMEDIAL ACTION PLAN FOR SITE 4B ALLEGANY BALLISTICS LABORATORY WEST
VIRGINIA |
3/1/2007 |
|
CH2M HILL |
|
01843 |
NAVY RESPONSES
TO U S EPA REGION III AND WVDEP COMMENTS ON THE DRAFT FINAL FOCUSED
REMEDIAL INVESTIGATION FOR SITE 1 SOIL OPERABLE UNIT 4 (OU 4) ALLEGANY
BALLISTICS LABORATORY WEST VIRGINIA |
12/9/2005 |
|
NAVFAC MID
ATLANTIC |
|
01844 |
EMAIL WITH
COMMENTS ON THE DRAFT RECORDS OF DECISION FOR SITES 3 AND 10 ALLEGANY
BALLISTICS LABORATORY WEST VIRGINIA |
11/28/2006 |
J BARBER |
U S EPA REGION
III |
|
01846 |
EMAIL WITH
RESPONSE TO NAVY COMMENTS ON THE REMEDIAL INVESTIGATION FOR SITE 1
ALLEGANY BALLISTICS LABORATORY WEST VIRGINIA |
5/11/2006 |
J BARBER |
U S EPA REGION
III |
|
01848 |
LETTER
DISCUSSING THE WORK PLAN SCHEDULE FOR RCRA SITES HANDLED UNDER THE
CERCLA PROGRAM ALLEGANY BALLISTICS LABORATORY WEST VIRGINIA |
11/18/2005 |
T BASS |
WVDEP |
|
100 |
GUIDE TO
MANAGEMENT OF INVESTIGATION DERIVED WASTES (OSWER DIRE 9345.3-O3FS)
ALLEGANY BALLISTICS LABORATORY WEST VIRGINIA |
1/1/1992 |
|
U S EPA |
|
1015 |
RECORD OF
DECISION FOR SITE 1 OPERABLE UNIT 3 (OU 3) GROUNWATER, SURFACE WATER AND
SEDIMENT AT ABL |
4/1/1997 |
|
|
|
1016 |
GUIDANCE
DOCUMENT ON RULES OF THUMB FOR SUPERFUND REMEDY SELECTION |
8/1/1997 |
|
U S EPA |
|
1021 |
LETTER
REGARDING REVIEW OF WORK PLANS FOR SITE 1 AND SITE 7 |
3/27/1994 |
M STEWART |
HERCULES/ABL |
|
1023 |
LETTER
REGARDING THE REVIEW OF THE ISSUES INVOLVED IN CLEANING UP ENVIRONMENTAL
CONTAMINATION CAUSED BY CONTRACTORS ON GOVERNMENT OWNED PROPERTY |
6/29/1993 |
D HEIVILIN |
U S GAO |
|
1043 |
NIROP ABL
MINUTES OF RESTORATION ADVISORY BOARD (RAB) |
6/20/1995 |
|
|
|
1044 |
NIROP ABL
MINUTES OF RESTROATION ADVISORY BOARD (RAB) |
12/12/1995 |
|
|
|
1045 |
NIROP ABL
MINUTES OF RESTORATION ADVISORY BOARD (RAB) |
2/21/1996 |
|
|
|
1046 |
NIROP ABL
MINUTES OF RESTORATION ADVISORY BOARD (RAB) |
8/7/1996 |
|
|
|
1047 |
NIROP ABL
MINUTES OF RESTORATION ADVISORY BOARD (RAB) |
10/29/1996 |
|
|
|
1049 |
NIROP ABL
MINUTES OF RESTORATION ADVISORY BOARD (RAB) |
5/14/1997 |
|
|
|
1052 |
TRANSMITTAL
LETTER REGARDING DRAFT FINAL SITE 1 FOCUSED FEASIBILITY STUDY FOR
GROUNDWATER AND DRAFT FOCUSED FEASIBILITY STUDY FOR SITE 5 LANDFILL
CONTENTS AND SURFACE SOIL |
5/7/1996 |
J KIDWELL |
LANTDIV |
|
1053 |
LETTER TO ALL
RESTORATION ADVISORY BOARD MEMBERS FOR APPRICIATION OF WORK IN THE
ESTABLISHMENT OF RESTORATION ADVISORY BOARD AND TO RESCHEDULE MEETING |
2/8/1996 |
L WILLIAMS |
NAVAL SEA
SYSTEMS COMMAND |
|
1067 |
LETTER
REGARIDNG INVITATION TO PARTICIPATE IN THE DEDICATION CEREMONY FOR NEW
GROUNDWATER TREATMENT PLANT AND EXTRACTION SYSTEM |
2/1/1999 |
C UNDERWOOD |
STATE OF WEST
VIRGINIA |
|
1068 |
LETTER
REGARIDNG INVITATION TO PARTICIPATE IN THE DEDICATION CEREMONY FOR NEW
GROUNDWATER TREATMENT PLANT AND EXTRACTION SYSTEM |
1/27/1999 |
J ROCKEFELLER |
U S SENATE |
|
1069 |
LETTER
REGARIDNG INVITATION TO PARTICIPATE IN THE DEDICATION CEREMONY FOR NEW
GROUNDWATER TREATMENT PLANT AND EXTRACTION SYSTEM |
12/4/1998 |
R BYRD |
U S SENATE |
|
1070 |
LETTER
REGARDING SUCCESSFUL PARTNERSHIP BETWEEN NAVY, CERCLA, RCRA, STATE OF
WEST VIRGINIA AND STATE OF MARYLAND |
1/1/1999 |
T BASS |
WVADEP OWM |
|
1073 |
LETTER
REGARDING REVIEW OF DRAFT FINAL SITE MANAGEMENT PLAN |
11/10/1997 |
T BASS |
WVADEP OWM |
|
1080 |
LETTER
REGARDING PROPOSED AGENDA FOR INSTALLATION RESTORATION PROGRAM PROJECT
MANAGERS MEETING |
1/14/1997 |
J KIDWELL |
LANTDIV |
|
1095 |
LETTER AND
COMMENTS ON ABL CONFIRMATION STUDY (CS) REPORT DATED JUNE 1986 |
7/30/1986 |
J BAILEY |
LANTDIV |
|
1098 |
LETTER
REGARDING ABL CONFIRMATION STUDY, SECOND ROUND VERIFICATION STEP
SAMPLING USATHAMA RECOMMENDED HOLDING TIME FOR HEXAVALENT CHROMIUM |
6/6/1985 |
J BAILEY |
LANTDIV |
|
11 |
TRANSMITTAL
LETTER FOR THE FINAL INTERIM REMEDIAL INVESTIGATION REPORT ALLEGANY
BALLISTICS LABORATORY WEST VIRGINIA |
1/15/1990 |
R MCALISTER |
ROY F WESTON
INC |
|
110 |
TRANSMITTAL
LETTER FOR THE DRAFT REMEDIAL INVESTIGATION REPORT FOR ALLEGANY
BALLISTICS LABORATORY WEST VIRGINIA |
10/20/1992 |
D MCBRIDE |
HERCULES/ABL |
|
1101 |
LETTER
REGARDING THE COMPLETION TO THE FIRST ROUND OF SAMPLING FOR NACIP
CONFIRMATION STUDY |
1/24/1985 |
J BAILEY |
LANTDIV |
|
111 |
TRANSMITTAL
LETTER FOR THE DRAFT REMEDIAL INVESTIGATION REPORT FOR ALLEGANY
BALLISTICS LABORATORY WEST VIRGINIA |
10/15/1992 |
G MOTT |
CH2M HILL |
|
112 |
REQUEST TO
CONDUCT PRESENTATION MEETING FOR THE DRAFT REMEDIAL INVESTIGATION REPORT
FOR ALLEGANY BALLISTICS LABORATORY WEST VIRGINIA |
10/26/1992 |
D MCBRIDE |
HERCULES/ABL |
|
113 |
TRANSMITTAL
LETTER FOR THE DRAFT REMEDIAL INVESTIGATION REPORT FOR ALLEGANY
BALLISTICS LABORATORY WEST VIRGINIA |
12/15/1992 |
D MCBRIDE |
HERCULES/ABL |
|
114 |
TRANSMITTAL
LETTER FOR THE DRAFT REMEDIAL INVESTIGATION REPORT FOR ALLEGANY
BALLISTICS LABORATORY WEST VIRGINIA |
12/4/1992 |
D MCBRIDE |
HERCULES/ABL |
|
1149 |
LETTER
REGARDING SITE 7 ABL SITE SUMMARY |
12/1/1994 |
J SZYKMAN |
LANTDIV |
|
115 |
TRANSMITTAL
LETTER FOR INSTALLATION RESTORATION PROGRAM MAPS ALLEGANY BALLISTICS
LABORATORY WEST VIRGINIA |
11/16/1992 |
D MCBRIDE |
HERCULES/ABL |
|
1153 |
LETTER AND
COMMENTS ON THE DRAFT FINAL WORK PLAN FOR SEGREGATING THE SOIL REMOVED
FROM SITE 7 |
6/14/1996 |
T BASS |
WVADEP OWM |
|
1154 |
LETTER WITH
ENCLOSED COMMENTS FOR SITE 7 BERYLLIUM LANDFILL |
5/8/1996 |
J KIDWELL |
LANTDIV |
|
1155 |
TRANSMITTAL
LETTER FOR DRAFT FINAL WORK PLAN SOIL SEGREGATION AND ANALYSIS |
5/16/1995 |
G MILLER |
OHM
REMEDIATION SERVICES |
|
1159 |
LETTER AND
COMMENTS ON THE REVIEW OF DRAFT FINAL WORK PLAN SITE 7 |
7/1/1996 |
B BEACH |
U S EPA REGION
III |
|
116 |
TRANSMITTAL
LETTER FOR THE DRAFT REMEDIAL INVESTIGATION REPORT FOR ALLEGANY
BALLISTICS LABORATORY WEST VIRGINIA |
11/4/1992 |
D MCBRIDE |
HERCULES/ABL |
|
1160 |
LETTER
REGARDING THE MEDICAL REVIEW OF INSTALLATION RESTROATION PROGRAM
DOCUMENTS FOR ABL (HEALTH AND SAFETY PLAN REVIEW) |
5/3/1994 |
W THOMAS |
NEHC |
|
1165 |
LETTER
REGARDING SITE 7 SEGREGATED SOIL DISPOSAL (GUIDANCE ON SEEKING
EXTENSION) |
12/18/1996 |
T BASS |
WVADEP OWM |
|
1166 |
LETTER AND
COMMENTS ON THE ACCEPTANCE OF THE REVIEW ON THE ENGINEERING
EVALUATION/COST ANALYSIS (EE/CA) |
9/19/1996 |
T BASS |
WVADEP OWM |
|
1167 |
LETTER AND
COMMENTS ON THE ACCEPTANCE OF THE REVIEW ON THE DRAFT FINAL WORK PLAN
FOR SOIL SEGREGATION AND ANALYSIS FOR THE BERYLLIUM LANDFILL, SITE 7 |
9/30/1996 |
T BASS |
WVADEP OWM |
|
1168 |
LETTER AND
COMMENTS ON THE ACCEPTANCE OF REVIEW OF THE FINAL WORK PLAN FOR SOIL
SEGREGATION AND ANALYSIS FOR THE BERYLLIUM LANDFILL, SITE 7 |
10/4/1996 |
T BASS |
WVADEP OWM |
|
117 |
TRANSMITTAL
LETTER FOR THE DRAFT REMEDIAL INVESTIGATION REPORT FOR ALLEGANY
BALLISTICS LABORATORY WEST VIRGINIA |
11/4/1992 |
D MCBRIDE |
HERCULES/ABL |
|
1170 |
HISTORY AND
CHRONOLOGY OF EVENTS, SITE 7 BERYLLIUM LANDFILL, ABL, OCTOBER 2, 1996 |
10/2/1996 |
|
|
|
119 |
FAX AND
COMMENTS OF THE DRAFT REMEDIAL INVESTIGATION REPORT FOR ALLEGANY
BALLISTICS LABORATORY WEST VIRGINIA |
1/4/1993 |
J SZYKMAN |
LANTDIV |
|
1192 |
TRANSMITTAL
LETTER FOR FINAL RECORD OF DECISION (ROD) FOR SITE 1 OPERABLE UNIT 3:
GROUNDWATER, SURFACE WATER AND SEDIMENT |
5/7/1997 |
D ANDERSON |
NAVAL SEA
SYSTEMS COMMAND |
|
12 |
TRANSMITTAL
LETTER FOR THE INTERIM REMEDIAL INVESTIGATION REPORT ALLEGANY BALLISTICS
LABORATORY WEST VIRGINIA |
10/17/1989 |
R MCALISTER |
ROY F WESTON
INC |
|
1228 |
LETTER AND
COMMENTS ON REVIEW OF FINAL FOCUSED FEASIBILITY STUDY SITE 10
GROUNDWATER |
3/27/1998 |
T BASS |
WVADEP OWM |
|
1229 |
LETTER AND
COMMENTS ON REVIEW OF DRAFT FOCUSED FEASIBILITY STUDY SITE 10
GROUNDWATER |
1/27/1997 |
D MCBRIDE |
ALLIANT |
|
1230 |
LETTER AND
COMMENTS ON REVIEW OF DRAFT WORK PLAN SITE 10 GROUNDWATER |
8/13/1998 |
D MCBRIDE |
ALLIANT |
|
1231 |
TRANSMITTAL
LETTER ON FOCUSED FEASIBILITY STUDY SITE 10 GROUNDWATER COMMENTS |
4/6/1998 |
D HAYES |
LANTDIV |
|
1232 |
TRANSMITTAL
LETTER ON FOCUSED FEASIBILITY STUDY SITE 10 GROUNDWATER COMMENTS |
4/6/1998 |
D HAYES |
LANTDIV |
|
1233 |
LETTER
REGARDING REGULATORY AUTHORITY OVER SITE 1 PROPOSED GROUNDWATER
TREATMENT FACILITY |
10/1/1996 |
W NOE |
MARYLAND
DEPARTMENT OF THE ENVIRONMENT |
|
1234 |
LETTER
REGARDING REVIEW OF DRAFT WORK PLAN REMEDIAL INVESTIGATION AND
FEASIBILITY STUDY OF SITE 11 |
10/3/1996 |
D HULBURT |
ALLIANT |
|
1235 |
LETTER
REGARDING REVIEW AND ACCEPTANCE OF THE ADVANCED SITE INSPECTION SITE 11 |
10/16/1996 |
T BASS |
WVADEP OWM |
|
1236 |
LETTER
REGARDING SITE 1 CLARIFICATION OF THE NORTH BRANCH POTOMAC RIVER
CLASSIFICATION, NPDES MIXING ZONE DISCHARGE, AND 7 DAY, 10 YEAR LOW FLOW
(7Q10) |
5/6/1996 |
T BASS |
WVADEP OWM |
|
124 |
FAX OF MAP
DEPICTING THE THREE PROPOSED SURFACE WATER SAMPLING LOCATIONS ALLEGANY
BALLISTICS LABORATORY WEST VIRGINIA |
8/27/1992 |
D BITTERMAN |
CH2M HILL |
|
1243 |
LETTER
REGARDING DRAFT WORK PLAN PHASE II RCRA FACILITY INVESTIGATION |
11/18/1996 |
D MCBRIDE |
ALLIANT |
|
1244 |
LETTER AND
COMMENTS ON THE REVIEW OF SITE 11, REMEDIAL INVESTIGATION AND
FEASIBILITY STUDY (RI/FS) |
11/18/1996 |
T BASS |
WVADEP OWM |
|
1245 |
TRANSMITTAL
LETTER FOR DRAFT FOCUSED FEASIBILITY STUDY FOR SOIL AND GROUNDWATER AT
SITE 10 |
11/22/1996 |
G MOTT |
CH2M HILL |
|
1248 |
LETTER
REGARDING SITE 1 DNAPL TARGET WELLS GROUNDWATER REMEDIATION (REVIEW OF
GROUNDWATER MONITORING WELL INSTALLATION FOR SITE 1) |
10/1/1997 |
T BASS |
WVADEP OWM |
|
125 |
TRANSMITTAL OF
DRAFT INSTALLATION RESTORATION PLANS FOR ALLEGANY BALLISTICS LABORATORY
WEST VIRGINIA |
6/10/1992 |
D MCBRIDE |
HERCULES/ABL |
|
1252 |
TRANSMITTAL
LETTER FOR FINAL RECORD OF DECISION FOR SITE 5 LANDFILL CAP AND SURFACE
SOIL |
1/28/1997 |
D ANDERSON |
NAVAL SEA
SYSTEMS COMMAND |
|
1259 |
SIGNATURE PAGE
FOR RECORD OF DECISION |
2/12/1997 |
|
|
|
126 |
TRANSMITTAL
LETTER FOR THE DRAFT INSTALLATION RESTORATION PROGRAM PLANS ALLEGANY
BALLISTICS LABORATORY WEST VIRGINIA |
6/9/1992 |
D MCBRIDE |
HERCULES/ABL |
|
1265 |
LETTER AND
COMMENTS ON THE REVIEW OF THE DRAFT PHASE I AQUIFER TESTING GROUNDWATER
REMEDIATION |
11/18/1997 |
T BASS |
|